Our thinking · The 2026 thesis

Power decides what gets built.

The binding constraint on AI capacity has moved from silicon to electricity. That change rewrites who holds the advantage in the buildout, and it will not stay true forever. Scroll: this is the argument, with the evidence.

Scroll
The binding constraint
What holds a new AI campus back?
SILICON
POWER
2023
01The inversion

The buildout began as a chip story.

Allocation queues, export controls, the price of an H100. In 2023, silicon was the wall every AI project hit first.

Silicon scarcity is cyclical.

Fabs expand, packaging debottlenecks, and every hardware generation loosens the last one's allocation. Electricity is different: generation, transmission and substations are built on a decade clock, by institutions that do not move at software speed.

By 2026, the wall moved.

The constraint shifted from the order book at the fab to the interconnection queue at the utility. The first question asked of a new AI campus is no longer how many GPUs it can get. It is how many firm megawatts it can deliver, and when.

Median wait · grid request → operation
2,060+ GW now waiting in queues
<2y
2000–07
~3y
2008–14
~3.5y
2015–17
>4y
2018–21
~4.5y
2022–24
>5y
2025
Years in the interconnection queue, by year the project was completed · LBNL
02The queue

The wait keeps getting longer.

Lawrence Berkeley National Laboratory has tracked the interconnection queue for two decades. Projects completed in the early 2000s waited under two years for their grid connection.1

Now it is more than five years.

For projects completed in 2025 the median wait passed five years, with over 2,000 gigawatts of capacity standing in line. In the primary data-center markets, developers plan on five to seven.1

A greenfield start today is a 2031 story.

That is the consequence in one line. An AI campus that begins today on an unpowered site waits out the queue before it earns a dollar. The demand curve is not waiting for it.

The conversions · publicly reported
Retired coal plant
Homer City, Pennsylvania
WAS1,884 MW coal plant, shuttered 2023
NOW$10B AI campus · up to 4.5 GW of new gas generation
0MW · ALREADY CONNECTED
Idle aluminum smelter
Hawesville, Kentucky
WASCentury Aluminum smelter · energized substation
NOWSold for a reported $200M · data-center campus
0MW · THROUGH EXISTING LINES
Bitcoin mining fleet
Core Scientific, six sites
WASBitcoin mining load across six facilities
NOWContracted to CoreWeave for AI, twelve years
0MW · ABOUT $10B OVER 12 YEARS
03The fast path

The way around the queue is already built.

American industry spent a century building industrial-scale grid connections, then walked away from many of them. Homer City is the flagship: a retired 1,884-megawatt coal plant becoming a $10 billion AI campus on its existing interconnections.2

The smelters are next.

Century Aluminum's Hawesville smelter, with roughly 480 megawatts available through an energized on-site substation, sold to a data-center developer for a reported $200 million.3 Alcoa has since put ten more smelter sites in front of data-center buyers.4

The miners moved first.

CoreWeave has contracted roughly 590 megawatts across six Core Scientific bitcoin-mining sites, about $10 billion of revenue over twelve years, on infrastructure originally built for hashrate.5

Six trades, one build
The asset and the capability live in different companies.
04The mismatch

The owners are not operators.

Industrial companies, miners, utilities, developers: almost none of the holders of these sites has ever run compute. The scarce asset and the capability to monetize it live in different companies, six specialist trades apart.

The demand and the capital come first.

A creditworthy tenant and the capital structured against that contract. Without these two, nothing else on the site is financeable.

Then power and the building.

Proving the megawatts are firm, and retrofitting a shell built for another century into liquid-cooled white space.

Then the machine and the business.

Silicon, fabric, and the operating layer that meters and sells compute. Six trades that have rarely worked together, and no single vendor sells the assembly. The winners of this window will be the ones who get all six to land in the right order.

05The pivot

What converts a site is not construction. It is a signature.

A creditworthy tenant on a multi-year, take-or-pay contract turns projected revenue into collateral, and collateral is what project finance runs on: debt raised against the contract rather than against the owner.

$0B
OpenAI's reported commitment to one neocloud6
0%
of CoreWeave's 2024 revenue from a single anchor, per its IPO filing7
0 yrs
the contract length lenders amortize a build against
06The window
2026
The advantage of an already-powered site is real, and it is not permanent.

What we do about it. Neocloud Group exists for the two sides this thesis creates. If you hold a powered site, or the capital to acquire one, we take you from shell to a live, revenue-generating neocloud: feasibility, tenant, capital, build and operations, run as one plan. If you buy compute at scale, we front sites that have been qualified the way your own diligence would qualify them. The thesis is public. The execution is the engagement.

Sources

  1. Lawrence Berkeley National Laboratory, "Queued Up: 2025 Edition," Energy Markets & Policy. emp.lbl.gov/queues
  2. Utility Dive, "Largest US gas-fired power plant planned for data centers in Pennsylvania," April 2025; Homer City Redevelopment project materials. utilitydive.com
  3. Engineering News-Record, "Fluor Tapped for Early Work on 480-MW Kentucky Data Center Campus"; Louisville Public Media, February 2026. enr.com
  4. Data Center Dynamics, "Alcoa looks to sell 10 aluminum smelting plants to data center developers." datacenterdynamics.com
  5. Core Scientific Form 8-K, June 2024, and subsequent contract expansions through February 2025. sec.gov
  6. CoreWeave, "CoreWeave's Agreement with OpenAI to Deliver AI Infrastructure," March 2025. coreweave.com
  7. CoreWeave Form S-1, March 2025.
  8. Synergy Research Group via TechInsights, "Neoclouds Will Reach $180 Billion in Revenues by 2030." techinsights.com

All sources accessed July 2026. Figures are as publicly reported at their dates; the thesis is re-issued annually.

Hold the scarce input?

Tell us what you have: the site, the load, or the mandate. We'll come back with a straight first read.

Start a conversation